Solar photovoltaic net news: on July 11, national energy bureau announced the 2019 state subsidies for photovoltaic power generation project as a result, affects the photovoltaic pv for finally settled. This paper analyzes the various provinces and cities after the bidding each type of photovoltaic & other Benchmarking & throughout; ( On average) Electricity situation, main conclusions are as follows:
the bidding, a total of 22 provinces ( Autonomous regions and municipalities) 3921 projects in 2019 countries for subsidies range, with a total installed capacity of 2278. 86. 42 million kw. The ordinary photovoltaic power station installed capacity of 1812. 33. 16 million mw, accounting for 80% of the total subsidy capacity; Industrial and commercial distributed photovoltaic projects installed capacity of 466. 53. 26 million mw, accounting for 20% of the total capacity of subsidies.
in the class III resources include: hebei, shanxi, Shanghai, jiangsu, zhejiang, anhui, jiangxi, shandong, henan, hubei, hunan, guangdong, guangxi, chongqing, guizhou, shaanxi.
this year, a policy issued by the National Development and Reform Commission (NDRC) the name of pv electricity price benchmarking to guide prices, on the basis of conducting the photovoltaic bids, and photovoltaic bidding results, for the various provinces and cities of photovoltaic (pv) set a new & other; Benchmarking & throughout; Electricity price.
from the perspective of electricity price bidding results, overall the results of the bidding price range from 0. 2795-0. Between 5530, according to the three resources area to differentiate and three kinds of photovoltaic power station after electricity price range is as follows:
also comb for you the project number and capacity of the different provinces. Included in the project bidding subsidies from the provinces as shown in figure 2, the top three, respectively is, zhejiang, guizhou, shanxi capacity above 2 million kilowatts, three provinces combined capacity has accounted for 40% of the total capacity of subsidies. However, from three provinces resources, and zhejiang are three kinds of resources in guizhou area, shanxi for three kinds of resources in southern district, has just entered the 2 kinds of resources in northern area, the three provinces of resources situation and not to reduce electricity cost too much contribution.
can be seen from the figure 2 also most of the provinces with ordinary photovoltaic power station, and zhejiang industrial and commercial photovoltaic power station obviously occupied more than the province more than 50% of capacity. Can be more clearly see from figure 3, occupies the absolute dominant position in the industry and commerce distributed in zhejiang province, one of provincial industrial and commercial distributed capacity to occupy 33% of the total capacity of the industrial and commercial distributed, occupying 46% of the total project amount distributed industry and commerce.
ordinary photovoltaic power station, in addition to zhejiang, capacity and number of ranking and total capacity and total number of ranking no too big difference, as shown in figure 5 and figure 6.
solar photovoltaic network statement: this information is reproduced from the power grid cooperation media or other Internet website, solar photovoltaic network published the article for the purpose of the information, does not mean that agree with his point of view or confirm its description. The article content is for reference only.
'photovoltaic (pv) of the world' this is a comprehensive system to introduce photovoltaic summary of past, present and future of the development of corpus, wide-ranging, and can meet the needs of different readers. This paper not only includes editor Wolfgang & middot; Dr Parr, herself, in its new energy career of more than 50 years, the deep understanding of the development of photovoltaic (pv) and system summary, also include the global photovoltaic industry professionals engaged in new energy or a review of the photovoltaic difficult development,