Notable is, this is ja solar first expansion project, after the return to A shares also fired 2020 photovoltaic industry expansion of the first shot. After tong wei, longji, a photovoltaic giant blockbuster expansion plans. On January 11, love xu technology released over the next three years, 2020 ~ 2022) Expansion program, high efficiency crystalline silicon solar cell production capacity at the end of 2020 reached 22 gigawatts (gw). Second phase 5 gw battery + 5 gw components, plan in December 2023 reaches producing. This paper statistics the September to today issued a total of 2. 85 gw pv power plant EPC and 1. 9 gw component bid opening information. It is understood that the project construction period is expected to 8 months, a total investment of about 11. 300 million yuan. On February 18th, ja solar photovoltaic leading enterprises released the annual output of 10 gw efficient battery and 10 gw effective component expansion plans, the solar portal, a total investment of about 10. 2 billion yuan. Purport to create highly intelligent automation, informationization, with batteries and components for the integration of production and manufacturing base. In addition, in the same day, ja solar also released 3. 6 gw efficient battery upgrade project plan, a wholly owned subsidiary of ja solar co. , LTD. (three or four workshop Hereinafter referred to as & other; NingJin three or four workshop & throughout; ) For technical upgrading, in order to realize the annual output of 3. 6 gw efficient battery products production capacity. February 18, wind power projects in henan, China solar energy network, ja said, according to the business strategy planning will the project 5 gw efficient battery and 10 gw efficient components and supporting project is adjusted for 10 gw efficient battery and 10 gw efficient components and related projects. Specifically, CGNPC in development of 410 mw, 603 mw, guangzhou energy saving 220 mw, 345 mw, jin can group the people vote for 200 mw, 190 mw hubei energy group, huaneng 180 mw learned, on December 31, 2019, ja solar photoelectric high-tech industrial park management committee and yiwu information investment projects signed a framework agreement, solar net, can produce 5 gw efficient battery and 10 gw efficient components and supporting project cooperation intention. Solar energy engineering machine content are for reference only. Solar photovoltaic (pv) network statement: this information is reproduced from the media or other Internet web site, network cooperation photovoltaic network published the article for the purpose of the information, does not mean that agree with his point of view or confirm its description. In 2019, according to the Global Data Data ja solar photovoltaic modules Global shipments up to 10. 3 gw, become the world's second largest component suppliers. Solar photovoltaic webex: 2020 years, photovoltaic industry expansion gunfire constantly! It is worth noting that the solar panels, previously, tong wei and xu also love the leading enterprises in the photovoltaic cells release expansion plan respectively. Then, on February 11, tong wei shares issued 2020 - 2023 development plan, mentions a 2020 solar cells accumulated production capacity will reach 30 gw. Monocrystalline silicon raw materials and the project construction period is expected to be four years, points 2), monocrystalline silicon raw material issue 5 gw battery + 5 gw components, solar energy, plan in December 2021 reaches producing; Among them, the solar energy engineering machine unit of EPC project owners with soe/state is given priority to, this also reflected from the side, the polysilicon workshop work need in project bidding and parity, the wind power projects in henan state-owned enterprises has become the absolute main force.