Solar photovoltaic webex: datong city development and reform commission released today datong in March, 2020 issue of photovoltaic application monitoring lead base operation monthly report.
from the point of overall operation, solar equipment, datong base all items this month cant radiation for an average of 199 KWH/m 2. This month base total generating capacity of 127. 87 million KWH, solar net, rose to 103. 55%, reduce compared to 21. 12%. 2020 base accumulated generation 2. 88. 3 billion KWH, fell 27. 37%. Full use of hours for 123 hours this month, full use of hours for 277, fell 27. 37%.
from the point of operation indicators monitoring results, datong this month base single crystal components run averages 17 monitoring efficiency. 03%, the average nominal attenuation is 3. 39%; Single crystal components empirical averages 17 monitoring efficiency. 21%, Chinese solar net, nominal attenuation average of 1. 93%. Averages 16 a polycrystalline monitoring components operation efficiency. 04%, the average nominal attenuation is 3. 86%; Polycrystalline component empirical monitoring efficiency mean to 16. Attenuation rate 21%, solar energy, in the name of the mean of 2. 85%. Inverter the highest conversion efficiency & ge; 99%. All items after stripping out electricity, can effect comparing the measured averages 73 this month. 33%. Can effect comparing the measured averages 74 in 2020. 16%. Monitoring results show that the operation indexes are basically met the lead base requirements.
affected by new crown pneumonia outbreak in Shanxi Province electricity demand this month fell to a low level. In order to ensure the security of power grid operation, in accordance with the requirements for scheduling command, this month base appear larger light power brownouts, accumulative total capacity of about 24. 27 million kWh electricity loss,
solar photovoltaic network statement: this information is reproduced from the power grid cooperation media or other Internet website, solar photovoltaic network published the article for the purpose of the information, does not mean that agree with his point of view or confirm its description. The article content is for reference only.
this paper statistics the September to today issued a total of 2. 85 gw pv power plant EPC and 1. 9 gw component bid opening information. Among them, the EPC project owner units is given priority to with soe/state, this also reflected from the side, in project bidding and parity, the state-owned enterprises have become the absolute main force. In particular, solar portal, CGNPC in development of 410 mw, 603 mw, guangzhou energy saving 220 mw, 345 mw, jin can group of people for 200 mw, 190 mw hubei energy group, huaneng power 180 mw